Court of Appeal of L’Aquila, 13 December 2025, No. 1329

Arbitration proceedings conducted between the client and the contractor do not produce effects interrupting the limitation period in relation to the works supervisor, even though the latter may be called upon to answer jointly and severally for the same construction defects, given that the rules on preclusion are not subject to the application of Article 1310 of the Civil Code and the instances of interruption are exhaustive in nature, not susceptible to extensive application.