An arbitration clause inserted in a public procurement contract, pursuant to Article 241 of Legislative Decree No. 163/2006 as amended by Article 1, paragraph 19, of Law No. 190/2012, is null and void where the prior reasoned authorisation by the governing body of the contracting authority is lacking. Such authorisation constitutes a requirement for the validity of the clause and cannot be identified with the mere resolution approving the contract containing the arbitration agreement, as it must result from a formal act specifically referring to the submission to arbitration of disputes arising from the performance of the contract.
Methodological notes
standard
How to cite
Tribunale of Napoli, 19 December 2025, No. 12059, «Court of Naples, 19 December 2025, No. 12059», in Arbitration in Italy, https://www.arbitratoinitalia.it/en/decisione/court-of-naples-19-december-2025-no-12059-1770761756-8296/